Checking in at Westland Distillery – Skagit Valley Campus
September 30, 2020
/
![](https://www.tricocompanies.com/wp-content/uploads/2020/09/Westland-Collage-09.16.20.jpg)
TRICO’s civil team is prepping the site for rackhouses 1 & 2 footings, foundations, and tilt panel casting beds. Once casting beds are poured and cured, the commercial team will start forming and pouring tilt panels. The site will go from flat to a vertical building in just a few days span of time!
View Project