Phase 2 of Lot 72 Apron Improvements at Port of Skagit
July 8, 2021
/
Civil crews have completed excavation of unsuitable material from the asphalt prism and have imported nearly 23,000 tons to date of structural fill material. Next will be placement of the base course material with paving set for mid-late July. Weather has been beautiful and the earthwork has been running smoothly!